Huawei Horinger

Huawei Horinger is an AI data center in Horinger, China, owned by Huawei. Epoch AI estimates it draws 170 MW for computing, rising to 351 MW by Feb 2028.

  • 170 MWfor computing now, #34 of the 96 Epoch AI tracks
  • 351 MWplanned by Feb 2028
  • $6.4 billionbuilt so far, Epoch AI's estimate in 2025 dollars
170 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW100 MW200 MW300 MW400 MW20242025202620272028Oct 8, 2023: 0 MWJun 11, 2025: 42 MWMay 12, 2026: 87 MWAug 18, 2026: 170 MWDec 22, 2026: 216 MW (projected)Feb 17, 2028: 351 MW (projected)0 MW100 MW200 MW300 MW400 MW20242025202620272028Oct 8, 2023: 0 MWJun 11, 2025: 42 MWMay 12, 2026: 87 MWAug 18, 2026: 170 MWDec 22, 2026: 216 MW (projected)Feb 17, 2028: 351 MW (projected)
  1. Epoch AI's projection

    Building 6 (South Zone) is operational (estimate). This was the only new building under construction as of August 2026. We estimate the operational date based on an average of (1) previous buildings taking about 2 years on average from starting the building shell to becoming operational at ~full capacity, (2) a similar building at the Huawei Wuhu campus taking an estimated 550 days to become fully operational. Building 6 can reportedly support 100,000 AI accelerator cards and will deploy Huawei Ascend 950 chips. Based on the timing, we assume it has capacity for 100,000 Ascend 950DT chips (Ascend 950DT is ramping a few months later than 950PR). As with the other buildings, we multiply this capacity by the reported rack occupancy rate for the Horinger New Area (about 76%).

    351 MW for computing (was 216 MW)439 MW in all5 buildings running
  2. Epoch AI's projection

    In the West Zone, Building 2 is operational (estimate). A local government announcement said a "completion acceptance filing" was completed for Building 2 around September 23, 2026, "marking a critical step toward the project's entry into operation". We assume this corresponds to structural completion, since there was minimal construction activity by August 18th. We then allow 3 more months for a full fit-out of AI servers.

    216 MW for computing (was 170 MW)271 MW in all4 buildings running
  3. In the South Zone, Building 5 is operational, based on its structural completion, and the colored motion artifacts on the some of the cooling tower fans. Building 6 (South Zone) is under construction. In the West Zone, Building 3 has not begun construction.

    170 MW for computing (was 87 MW)212 MW in all3 buildings running
  4. In the West Zone, Building 2 is structurally complete but still has some construction equipment around it.

    87 MW for computing109 MW in all2 buildings running
  5. Building 4 is operational, based on its structural completion, the colored motion artifacts on some of the cooling tower fans, and cars parked out front (between the main building and the backup generator enclosure). Building 5 is almost structurally complete, but there is still some work to do in front of the backup generator enclosure.

    87 MW for computing (was 42 MW)109 MW in all2 buildings running
  6. Building 1 appears to have condensed water vapor above some cooling towers, suggesting they are still operating. Cooling towers have been added to Building 4, but we do not see any condensed water vapor, and there is still a crane over the building. So we don't think Building 4 is operational at full capacity yet.

    42 MW for computing53 MW in all1 building running
  7. In the West Zone, Building 1 is operational, based on its structural completion and colored motion artifacts on some of the cooling tower fans.

    42 MW for computing53 MW in all1 building running
  8. In the South Zone, paving and landscaping around Building 4 is mostly complete, while Building 5 still needs cooling and backup generators to be installed.

    No power for computing yet
  9. In the West Zone, Building 1 is structurally complete. In the South Zone, Building 4 is structurally complete except for several cooling towers to be installed later. Buildings 2 (West Zone) and 5 (South Zone) have shells under construction.

    No power for computing yet
  10. Land clearing begins simultaneously for all three zones (West, North, and South) after an official ceremony. The West and South zones later have the cooling capacity indicative of AI workloads, while the North Zone does not.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Aug 18, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

170 MWIT power, for the computersAug 18, 2026
212 MWtotal power, cooling included
351 MWIT power planned by Feb 2028
81,000computing power, counted as Nvidia H100 chips
$6.4 billioncapital cost so far: $4.4 billion for chips and computers, $2.0 billion for the buildings, power and land
$13 billioncapital cost once finished, by Feb 2028
$0.2 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Huawei

Uses it

Not known

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
Ascend 910CHuawei104,716 est.Aug 18, 2026Building 5 (South Zone)
Ascend 910BHuawei7,694 est.Jun 11, 2025Building 1 (West Zone)
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Huawei Horinger in Epoch AI's directoryepoch.ai
  2. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/huawei-horinger