Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 3 is estimated to be operational. This is estimated from the timeline of similar buildings at other Meta sites.
218 MW for computing (was 118 MW)273 MW in all3 buildings running Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.
118 MW for computing (was 87 MW)147 MW in all2 buildings runningBuilding 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2.
87 MW for computing114 MW in all1 building runningBuilding 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.
87 MW for computing114 MW in all1 building runningLand clearing starts for new building.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Oct 26, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 53,061 est. | Oct 26, 2026 | GB300 NVL72 assumed from commissioning timeline and estimates from https://epoch.ai/data/ai-chip-owners . Count = Total IT power / IT overhead / server power x 72. |
Los Lunas, New Mexico
Address in Epoch AI's records: 4250 Messenger Lp, Los Lunas, NM 87031.
Also in New Mexico
More of Meta's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Meta fact sheetdatacenters.atmeta.com
- Air quality permit for expansiondrive.google.com
- Construction contractor page for the sitefortisconstruction.com
- Meta Los Lunas in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-los-lunas