Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Buildings 8-12 are operational. In June of 2026 only a faint outline of buildings 10,11 and 12 is visible, estimating construction completion to be the end of 2027, alligning with expected completion by 2027. This final estimates adds three months to that for server installation.
683 MW for computing (was 284 MW)819 MW in all12 buildings running - Epoch AI's projection
Buildings 6 and 7 operational, estimated from roofs having been completed 9 months ago (similar timeline to AWS buildings at New Carlisle in 2025).
284 MW for computing478 MW in all7 buildings running Buildings 6 and 7 roof completed. Building 8 roof nearly completed. Building 9 roof half way up. No new operational buildings.
284 MW for computing341 MW in all5 buildings runningConfirmation that five buildings are fully equipped with cooling and backup generators.
284 MW for computing341 MW in all5 buildings runningBuildings 1-5 are operational, based on roofs being completed 5 months ago and generators being installed by 2025-04-10.
284 MW for computing341 MW in all5 buildings runningGenerators and chillers still being installed on buildings 1-5.
No power for computing yetLand clearing begins
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jun 4, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| Trainium2 | Amazon | 326,555 est. | Jun 23, 2025 | Chip type assumed from Project Rainier announcement (Trainium2). 5 buildings operational. Count = buildings × chips per building, where chips per building = building power / (PUE × IT overhead factor × chip TDP). |
Canton, Mississippi
Address in Epoch AI's records: Amazon Data Services Inc, Madison Mega Site Nissan Parkway and Highway 22 Canton, Mississippi Madison County.
Also in Mississippi
More of Amazon's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Air Construction Permitdrive.google.com
- Backup diesel generator referenced in the permitcat.com
- New York Times article on Project Rainiernytimes.com
- SemiAnalysis article with imagery of Canton they have labeled as being an Amazon-Anthropic collaborationnewsletter.semianalysis.com
- Amazon Madison Mega Site in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/amazon-madison-mega-site