Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 3 (AKA CB5) is operational. On February 26, 2026, Terawulf stated that CB5 was expected to be energized by Q4 2026. However, based on the pace of Building 2, and comparisons to other projects like Stargate Abilene, we think this is optimistic. We expect a 3-month delay past the end of Q4 2026 to get to full operational capacity.
378 MW for computing (was 210 MW)441 MW in all3 buildings running Building 2 (AKA CB4) is operational. On February 26, Terawulf stated that CB4 was expected to be energized by Q3 2026.
210 MW for computing (was 42 MW)245 MW in all2 buildings runningBuilding 1 looks complete, consistent with it going operational back in May. Building 2 is mostly complete, with the row of backup generators on the east side of the building still being installed. Building 3 shell is complete, with rooftop coolers midway through installation, and no neighboring generators installed/visible yet.
42 MW for computing49 MW in all1 building runningBuilding 1 is operational. On February 26, Terawulf stated that CB3 was expected to be energized by mid-May 2026. A drone video commissioned from RAAD shows several cooling units operating on May 8. It's therefore likely that the building was fully operational around this date.
42 MW for computing49 MW in all1 building runningBuilding 1 appears to have a complete shell and cooling equipment. Building 2 shell is still under construction, but 17 cooling units are already loaded on the roof. The outline of Building 3 is visible at the foundation.
No power for computing yetLand clearing begins for Building 1 (AKA CB3).
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Oct 31, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Anthropic (likely)
No wider project named
Google, Blackstone
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v7 | 125,598 est. | Oct 31, 2026 | Building 2. The building is leased to Fluidstack, and likely contains Google TPUs, which are likely leased to Anthropic. We assume TPU v7 (Ironwood), since v7 is expected to dominate TPU production by mid-2026. Count = IT power / default AI chip IT overhead / TPU v7 TDP. |
Barker, New York
Address in Epoch AI's records: 7725 Lake Rd, Barker, NY 14012.
Also in New York
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Terawulf press release with details and timeline for Buildings 1-5investors.terawulf.com
- DCD article suggesting that Fluidstack will deploy Google TPUs at Lake Marinerdatacenterdynamics.com
- Announcement of Anthropic-Fluidstack partnership, including data center(s) in New Yorkanthropic.com
- Anthropic Lake Mariner in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/anthropic-lake-mariner