Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Expected operational date for the remaining tracked buildings (11, and 1-4) across the three campuses. This estimate is based on the previous buildings taking roughly 1.5 years from steel framing to complete operational status. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed.
338 MW for computing (was 213 MW)405 MW in all14 buildings running Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.
213 MW for computing255 MW in all9 buildings runningMiddle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on satellite imagery, northern campus Buildings 1-3 appear in late construction, with all roofs complete but nearby generator/cooling equipment still being installed for buildings 2-3. Building 4 is still early in construction. Eastern campus Buildings 5-9 appear complete and operational as expected. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed.
213 MW for computing (was 113 MW)255 MW in all9 buildings runningBuildings 5-9 (eastern campus) operational. New Albany’s Dec. 2024 report lists AWS partial occupancy for 5 buildings at the eastern campus. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed. The full IT power is much higher than 113 MW.
113 MW for computing136 MW in all5 buildings runningLand clearing begins for Buildings 5-9 (eastern campus).
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 18, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B200 | Nvidia | 46,847 est. | May 18, 2026 | Cumulative B200 quantity after northern Building 1 is added. The new cohort uses the Q1 2026 eligible-chip sales mix after applying the three-month deployment lag. Epoch Chip Sales |
| H100 | Nvidia | 64,944 est. | Dec 1, 2024 | Initial modeled H100 capacity in Buildings 5-9. Uses the Q3 2024 H100-equivalent sales mix with a three-month deployment lag. The 75% H100 share of combined Hopper compute is a model assumption because Epoch does not separately report H100 and H200 sales. Epoch Chip Sales Methodology |
| Trainium2 | Amazon | 36,702 est. | Mar 12, 2026 | Cumulative Trainium2 quantity after Buildings 10 and 12-14 are added using the Q4 2025 eligible-chip sales mix and a three-month deployment lag. Epoch Chip Sales |
| H200 | Nvidia | 23,603 est. | Mar 12, 2026 | Cumulative H200 quantity after Buildings 10 and 12-14 are added using the Q4 2025 eligible-chip sales mix. The residual Hopper allocation is assigned to H200 as a model assumption. Epoch Chip Sales Methodology |
New Albany, Ohio
Address in Epoch AI's records: 13360 Miller Rd NW.
Also in Ohio
More of Amazon's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- City of New Albany Project Updatesnewalbanyohio.org
- New Albany Community Development Report - Dec. 2024newalbanyohio.org
- New Albany Community Development Report - Aug. 2025newalbanyohio.org
- Article reporting first signing of the projectwosu.org
- AWS New Albany in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/aws-new-albany