Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 1 is operational (estimate). No additional chip deployment beyond the 18,400 GB300 GPUs has been publicly confirmed, so we continue to report the disclosed capacity allocated to Project Southgate, rather than speculate on further buildout.
41 MW for computing57 MW in all1 building runningBuilding 1's cooling capacity increased to 53 air-cooled chillers (20 fans each), up from 30 in Oct 2025. This is more than enough for the announced 18,400 GB300 GPUs, but construction does not quite look complete, so we expect another 3 months until it's operational.
No power for computing yetSatellite imagery shows 30 fully installed air-cooled chillers (20 fans each) on the roof, with room for many more. In the same month, Firmus reported that Project Southgate's "first stages are under construction in Tasmania and Melbourne". So we don't think the Southgate part of the building is operational yet.
No power for computing yetBuilding 1 site is cleared/vacant land; no construction visible yet (based on Google Earth historical imagery).
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Aug 9, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 18,400 disclosed | Aug 9, 2026 | Confirmed via company disclosure (Firmus press releases citing 18,400 GB300 GPUs for this Melbourne facility). Cooling capacity confirms this building can support at least this many chips (plus headroom); we report only the confirmed disclosed figure rather than speculating on additional capacity. |
Melbourne, Victoria, Australia
Epoch AI gives no street address for this site.
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Firmus Expands Project Southgate Across Australiafirmus.co
- Firmus Signs Multi-Year Agreement with Global Hyperscale Customer at Project Southgatefirmus.co
- CDC Melbournecdc.com
- Southgate Melbourne in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/southgate-melbourne