Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
6 buildings are operational. This is based on: 1. A regulatory filing for Building 6 with a completion date of 2027-07-30. Normally there is a follow-up filing for "tenant improvement" which involves building the interior, with a completion date 1-3 months after the initial filing. 2. A project deadline of EOY 2027 in the original tax abatement agreement 3. The similar 8-building project in Abilene taking an estimated 2 years and 2 months.
1.01 GW for computing (was 206 MW)1.29 GW in all6 buildings running - Epoch AI's projection
Building 2 operational. The completion date for Building 2 Tenant Improvement is 2026-11-07, about 2 months later than Building 1. We therefore add 2 months to the Building 1 operational date.
206 MW for computing (was 103 MW)265 MW in all2 buildings running - Epoch AI's projection
Building 1 operational. This regulatory document lists the completion date for Building 1 as 2026-09-12, the current status suggests this estimate will not be met. Based on the timeline seen at the Abilene,Texas site for the same building styles and the most recent imaged status, we estimate operability to occur 6 months after the state seen in Sept 2026.
103 MW for computing133 MW in all1 building running Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.
No power for computing yetConstruction on Building 1 and 2 looks about halfway to completion. Foundations and utility trenches are visible for Building 3-4. Building 5-6 have an outline. The substation appears to be expanding.
No power for computing yetBuilding 1 and 2 under construction.
No power for computing yetLand clearing begins
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Apr 16, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google (possibly)
Google DeepMind (possibly)
No wider project named
Not named
Crusoe, Hoffman
Serena
Claude, Texas
Address in Epoch AI's records: 10001 Lima Rd, Claude, TX 79019.
Also in Texas
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Amended tax abatement agreement, with updated blueprints on p.46co.armstrong.tx.us
- Original tax abatement agreement, with original blueprints and specs on the last pagedrive.google.com
- TABS database, with "Llano" data centers in the city of Claudetdlr.texas.gov
- Press release reports Google investing in a new data center in Armstrong Countyreuters.com
- Clean Air Act Initial Prevention of Significant Deterioration permit application.drive.google.com
- Goodnight in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/goodnight