Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 10 is operational (estimate). TDLR lists the construction completion date for Building 10 as 2028-05-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
1.40 GW for computing (was 1.26 GW)1.96 GW in all10 buildings running - Epoch AI's projection
Building 9 is operational (estimate). TDLR lists the construction completion date for Building 9 as 2028-04-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
1.26 GW for computing (was 1.12 GW)1.76 GW in all9 buildings running - Epoch AI's projection
Building 8 is operational (estimate). TDLR lists the construction completion date for Building 8 as 2028-04-17. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
1.12 GW for computing (was 980 MW)1.57 GW in all8 buildings running - Epoch AI's projection
Building 7 is operational (estimate). TDLR lists the construction completion date for Building 7 as 2027-11-12. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
980 MW for computing (was 840 MW)1.37 GW in all7 buildings running - Epoch AI's projection
Building 6 is operational (estimate). TDLR lists the construction completion date for Building 6 as 2027-10-04. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
840 MW for computing (was 700 MW)1.18 GW in all6 buildings running - Epoch AI's projection
Building 5 is operational (estimate). TDLR lists the construction completion date for Building 5 as 2027-09-08. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
700 MW for computing (was 560 MW)980 MW in all5 buildings running - Epoch AI's projection
Building 4 is operational (estimate). TDLR lists the construction completion date for Building 4 as 2027-08-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
560 MW for computing (was 420 MW)784 MW in all4 buildings running - Epoch AI's projection
Building 3 is operational (estimate). TDLR lists the construction completion date for Building 3 as 2027-05-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
420 MW for computing (was 280 MW)588 MW in all3 buildings running - Epoch AI's projection
Building 2 is operational (estimate). TDLR lists the construction completion date for Building 2 as 2027-04-19. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
280 MW for computing (was 140 MW)392 MW in all2 buildings running - Epoch AI's projection
Building 1 is operational (estimate). TDLR lists the construction completion date for Building 1 as 2027-02-15. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
140 MW for computing196 MW in all1 building running Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.
No power for computing yetSteel framing is underway for Buildings 1-3, and roofing is underway for Building 1.
No power for computing yetThe layout of Buildings 1-5 is visible. Steel framing has just started on Building 1.
No power for computing yetLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Sep 4, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Abilene, Texas
Address in Epoch AI's records: 175 Private Road 1604, Abilene, TX 79601, Shackelford County.
Also in Texas
More of Oracle's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Vantage data center page with power capacity, number of buildings, and first building timelinevantage-dc.com
- OpenAI Stargate expansion announcement mentioning Shackelford siteopenai.com
- Vantage LinkedIn post connecting the data center to OpenAI Stargateweb.archive.org
- TDLR filing for first building (other buildings are also on TDLR)tdlr.texas.gov
- OpenAI Stargate Shackelford in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/openai-stargate-shackelford