Being built · Abilene, Texas

OpenAI Stargate Shackelford

OpenAI Stargate Shackelford is an AI data center in Abilene, Texas, owned by Oracle and used by OpenAI. It is being built; Epoch AI projects 1.40 GW for computing by Nov 2028.

  • 1.40 GWplanned by Nov 2028
Being built
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW200 MW400 MW600 MW800 MW1 GW1.2 GW1.4 GW1.6 GW202620272028Aug 1, 2025: 0 MWAug 15, 2027: 140 MW (projected)Oct 19, 2027: 280 MW (projected)Nov 18, 2027: 420 MW (projected)Feb 11, 2028: 560 MW (projected)Mar 8, 2028: 700 MW (projected)Apr 4, 2028: 840 MW (projected)May 12, 2028: 980 MW (projected)Oct 17, 2028: 1.12 GW (projected)Oct 18, 2028: 1.26 GW (projected)Nov 11, 2028: 1.40 GW (projected)0 MW200 MW400 MW600 MW800 MW1 GW1.2 GW1.4 GW1.6 GW202620272028Aug 1, 2025: 0 MWAug 15, 2027: 140 MW (projected)Oct 19, 2027: 280 MW (projected)Nov 18, 2027: 420 MW (projected)Feb 11, 2028: 560 MW (projected)Mar 8, 2028: 700 MW (projected)Apr 4, 2028: 840 MW (projected)May 12, 2028: 980 MW (projected)Oct 17, 2028: 1.12 GW (projected)Oct 18, 2028: 1.26 GW (projected)Nov 11, 2028: 1.40 GW (projected)
  1. Epoch AI's projection

    Building 10 is operational (estimate). TDLR lists the construction completion date for Building 10 as 2028-05-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    1.40 GW for computing (was 1.26 GW)1.96 GW in all10 buildings running
  2. Epoch AI's projection

    Building 9 is operational (estimate). TDLR lists the construction completion date for Building 9 as 2028-04-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    1.26 GW for computing (was 1.12 GW)1.76 GW in all9 buildings running
  3. Epoch AI's projection

    Building 8 is operational (estimate). TDLR lists the construction completion date for Building 8 as 2028-04-17. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    1.12 GW for computing (was 980 MW)1.57 GW in all8 buildings running
  4. Epoch AI's projection

    Building 7 is operational (estimate). TDLR lists the construction completion date for Building 7 as 2027-11-12. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    980 MW for computing (was 840 MW)1.37 GW in all7 buildings running
  5. Epoch AI's projection

    Building 6 is operational (estimate). TDLR lists the construction completion date for Building 6 as 2027-10-04. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    840 MW for computing (was 700 MW)1.18 GW in all6 buildings running
  6. Epoch AI's projection

    Building 5 is operational (estimate). TDLR lists the construction completion date for Building 5 as 2027-09-08. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    700 MW for computing (was 560 MW)980 MW in all5 buildings running
  7. Epoch AI's projection

    Building 4 is operational (estimate). TDLR lists the construction completion date for Building 4 as 2027-08-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    560 MW for computing (was 420 MW)784 MW in all4 buildings running
  8. Epoch AI's projection

    Building 3 is operational (estimate). TDLR lists the construction completion date for Building 3 as 2027-05-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    420 MW for computing (was 280 MW)588 MW in all3 buildings running
  9. Epoch AI's projection

    Building 2 is operational (estimate). TDLR lists the construction completion date for Building 2 as 2027-04-19. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    280 MW for computing (was 140 MW)392 MW in all2 buildings running
  10. Epoch AI's projection

    Building 1 is operational (estimate). TDLR lists the construction completion date for Building 1 as 2027-02-15. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    140 MW for computing196 MW in all1 building running
  11. Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.

    No power for computing yet
  12. Steel framing is underway for Buildings 1-3, and roofing is underway for Building 1.

    No power for computing yet
  13. The layout of Buildings 1-5 is visible. Steel framing has just started on Building 1.

    No power for computing yet
  14. Land clearing begins.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Sep 4, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

None yetIT power, for the computersSep 4, 2026
None yettotal power, cooling included
1.40 GWIT power planned by Nov 2028
None yetcomputing power, counted as Nvidia H100 chips
–capital cost so far
$53 billioncapital cost once finished, by Nov 2028
–a year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Oracle

Uses it

OpenAI

Part of

Stargate

Investors

Oracle, OpenAI

Builders

Not named

Power from

Not named

Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Vantage data center page with power capacity, number of buildings, and first building timelinevantage-dc.com
  2. OpenAI Stargate expansion announcement mentioning Shackelford siteopenai.com
  3. Vantage LinkedIn post connecting the data center to OpenAI Stargateweb.archive.org
  4. TDLR filing for first building (other buildings are also on TDLR)tdlr.texas.gov
  5. OpenAI Stargate Shackelford in Epoch AI's directoryepoch.ai
  6. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/openai-stargate-shackelford