Stream Phoenix

Stream Phoenix is an AI data center in Goodyear, Arizona. Epoch AI estimates it draws 64 MW for computing, rising to 220 MW by Jan 2030.

  • 64 MWfor computing now, #66 of the 96 Epoch AI tracks
  • 220 MWplanned by Jan 2030
  • $2.4 billionbuilt so far, Epoch AI's estimate in 2025 dollars
64 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW200 MW250 MW20232024202520262027202820292030Oct 30, 2022: 0 MWMay 1, 2026: 64 MWJan 1, 2030: 220 MW (projected)0 MW50 MW100 MW150 MW200 MW250 MW20232024202520262027202820292030Oct 30, 2022: 0 MWMay 1, 2026: 64 MWJan 1, 2030: 220 MW (projected)
  1. Epoch AI's projection

    Although official promotional sources estimate the campus to be fully operational in 10-12 years, it is likely to be finished sooner than this given the empirical durations for other data center campuses as well as because AI building 6 has been expedited. The first AI building took approximately 24 months to complete. Assuming construction for a new building starts midway for every building, then the campus will be complete in 4 years for the 5 remaining buildings, since AI buildings 2 and 6 are both underway.

    220 MW for computing (was 64 MW)267 MW in all6 buildings running
  2. Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the building will be operational.

    64 MW for computing77 MW in all1 building running
  3. Major construction has finished on AI building 1, and AI building 6 has been expedited, as depicted by satellite imagery.

    No power for computing yet
  4. Construction beginning, as can be seen on satellite. Major renovations on western side of the non AI building (PX1), including adding generators and cooling towers.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of May 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

64 MWIT power, for the computersMay 1, 2026
77 MWtotal power, cooling included
220 MWIT power planned by Jan 2030
46,000computing power, counted as Nvidia H100 chips
$2.4 billioncapital cost so far: $1.7 billion for chips and computers, $0.8 billion for the buildings, power and land
$8.3 billioncapital cost once finished, by Jan 2030
$0.1 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Not named by Epoch AI

Uses it

Not known

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
H100Nvidia46,112 est.May 1, 2026This is for building 1; the shell is complete, and it should be operational as of this date. H100 stub retained but no count available.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Official page for the data center.streamdatacenters.com
  2. Official pre-construction planning document.streamdatacenters.com
  3. Stream Phoenix in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/stream-phoenix