Running · Pryor, Oklahoma

Google Pryor (North)

Google Pryor (North) is an AI data center in Pryor, Oklahoma, owned by Google and used by Google DeepMind (possibly). Epoch AI estimates it draws 368 MW for computing.

  • 368 MWfor computing now, #9 of the 96 Epoch AI tracks
  • $14 billionbuilt so far, Epoch AI's estimate in 2025 dollars
368 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW100 MW200 MW300 MW400 MW2020202120222023202420252026Aug 1, 2019: 0 MWJul 19, 2024: 53 MWSep 6, 2026: 368 MW0 MW100 MW200 MW300 MW400 MW2020202120222023202420252026Aug 1, 2019: 0 MWJul 19, 2024: 53 MWSep 6, 2026: 368 MW
  1. Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.

    368 MW for computing (was 53 MW)442 MW in all2 buildings running
  2. Building 2 looks almost complete, but still appears to have three cooling towers missing. We therefore expect another 3 months until full operation.

    53 MW for computing63 MW in all1 building running
  3. The new substation for Building 2 looks mostly complete, half of the cooling towers are installed. The black patch in the top left of the building suggests that the new roof is not quite complete.

    53 MW for computing63 MW in all1 building running
  4. Building 2 is being retrofitted from a warehouse. The roof is being painted white, and cooling towers and a new substation are being built just south of the building (based on later imagery).

    53 MW for computing63 MW in all1 building running
  5. Building 1 is operational, based on default roof-to-operational time.

    53 MW for computing63 MW in all1 building running
  6. Land clearing begins for Building 1.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Sep 6, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

368 MWIT power, for the computersSep 6, 2026
442 MWtotal power, cooling included
368 MWthe most Epoch AI projects here
637,000computing power, counted as Nvidia H100 chips
$14 billioncapital cost so far: $9.6 billion for chips and computers, $4.3 billion for the buildings, power and land
$14 billioncapital cost, finished
$0.3 billiona year to run (power, staff, upkeep, taxes, water)
2.3 million gallonsof water a day, Epoch AI's estimate (Jul 19, 2024)

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Google

Uses it

Google DeepMind (possibly)

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
TPU v5eGoogle77,886 est.Jul 19, 2024First operational capacity (Q2 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP.
TPU v5pGoogle23,466 est.Jul 19, 2024First operational capacity (Q2 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Google announces expansion of Pryor facilityblog.google
  2. Google 2025 Environmental Reportsustainability.google
  3. News of a 9 exaflop TPUv4 cluster in the Pryor data center, launched in 2022techcrunch.com
  4. Google Pryor (North) in Epoch AI's directoryepoch.ai
  5. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-pryor-north