Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.
368 MW for computing (was 53 MW)442 MW in all2 buildings runningBuilding 2 looks almost complete, but still appears to have three cooling towers missing. We therefore expect another 3 months until full operation.
53 MW for computing63 MW in all1 building runningThe new substation for Building 2 looks mostly complete, half of the cooling towers are installed. The black patch in the top left of the building suggests that the new roof is not quite complete.
53 MW for computing63 MW in all1 building runningBuilding 2 is being retrofitted from a warehouse. The roof is being painted white, and cooling towers and a new substation are being built just south of the building (based on later imagery).
53 MW for computing63 MW in all1 building runningBuilding 1 is operational, based on default roof-to-operational time.
53 MW for computing63 MW in all1 building runningLand clearing begins for Building 1.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Sep 6, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google DeepMind (possibly)
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v5e | 77,886 est. | Jul 19, 2024 | First operational capacity (Q2 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5p | 23,466 est. | Jul 19, 2024 | First operational capacity (Q2 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. |
Pryor, Oklahoma
Address in Epoch AI's records: 4581 Webb St, Pryor, OK 74361.
Also in Oklahoma
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Google announces expansion of Pryor facilityblog.google
- Google 2025 Environmental Reportsustainability.google
- News of a 9 exaflop TPUv4 cluster in the Pryor data center, launched in 2022techcrunch.com
- Google Pryor (North) in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-pryor-north