Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Buildings 3 is estimated complete by the end of Q1 2027, based on the current PowerHouse schedule. Added another three months to account for commissioning and server installation.
113 MW for computing (was 82 MW)197 MW in all3 buildings running Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans.
82 MW for computing (was 27 MW)114 MW in all2 buildings runningSatellite imagery shows Building 1 complete, with Building 2's yard work and early construction visible. Building 3 hasn't started yet, since the old building is still there.
27 MW for computing38 MW in all1 building runningBuilding 1 is scheduled to be fully online by this point, so we count the full 27 MW as operational here.
27 MW for computing (was 18 MW)38 MW in all1 building runningBuilding 1's second data hall scheduled to come online this month.
18 MW for computing25 MW in all1 building runningConversion starts at CTP-01 (Building 1). The data center was formerly owned by Capital One, now leased to CoreWeave. Source: https://www.datacenterdynamics.com/en/news/chirisa-secures-200-million-loan-to-fit-out-virginia-data-center-for-coreweave/
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 20, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B200 | Nvidia | 26,162 est. | May 20, 2026 | Estimated Building 2 B200 count using Building 2’s share of modeled CTP-02/03 IT power. |
| H100 | Nvidia | 22,100 est. | Apr 30, 2024 | Full CTP-01 estimate using the reported 27 MW critical capacity. Chip type and quantity are estimated from the power model. |
Chester, Virginia
Address in Epoch AI's records: 1401 Meadowville Technology Parkway, Chester, VA.
Also in Virginia
More of CoreWeave's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Chirisa secures $200 million loan to fit out VA Data center for CoreWeavedatacenterdynamics.com
- Blue Owl-led JV secures $750m to build out data centers for CoreWeavedatacenterdynamics.com
- Chirisa offers former Capital One data center in Virginia to hyperscalersdatacenterdynamics.com
- CoreWeave Chester VA in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-chester-va