Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.
47 MW for computing (was 19 MW)66 MW in all2 buildings runningNo more visible construction around either building, just a little equipment. Roads fully built around buildings as well.
19 MW for computing26 MW in all1 building runningBuilding 2 chiller installation is a little more than halfway complete, and chiller installation for the last data hall of Building 1 is also around halfway complete.
19 MW for computing26 MW in all1 building runningBuilding 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously incomplete, so we believe it was only operational at this point.
19 MW for computing26 MW in all1 building runningLand clearing for the site is almost complete. Informed using imagery on Google Earth
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Mar 31, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 12,750 est. | Mar 31, 2026 | Type estimated based on chip sales data. # of units estimated based on power for Building 2 and the rest of Building 1 that was completed since initial operation. |
| H100 | Nvidia | 12,963 est. | Jul 1, 2024 | Type estimated based on chip sales data. # of units estimated based on power for completed portions of Building 1. |
San Antonio, Texas
Address in Epoch AI's records: 3545 Wiseman Boulevard, San Antonio, TX 78251.
Also in Texas
More of Microsoft's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Phase 1 TDLRtdlr.texas.gov
- Phase 2 TDLRtdlr.texas.gov
- Phase 3 TDLRtdlr.texas.gov
- Phase 4 TDLRtdlr.texas.gov
- Microsoft SAT14 in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets