Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Estimated operational date of Building 6. Based on previous buildings being separated by about 5 months.
863 MW for computing (was 690 MW)1.03 GW in all5 buildings running - Epoch AI's projection
Estimated operational date of Building 5. Based on previous buildings being separated by about 5 months.
690 MW for computing (was 518 MW)828 MW in all4 buildings running - Epoch AI's projection
Estimated operational date of Building 4. Based on Building 4 construction looking about 10 months behind Building 2.
518 MW for computing (was 345 MW)621 MW in all3 buildings running - Epoch AI's projection
Estimated operational date of Building 3. Based on Building 3 construction looking about 4 months behind Building 2.
345 MW for computing (was 173 MW)414 MW in all2 buildings running - Epoch AI's projection
Estimated operational date of Building 2.
173 MW for computing207 MW in all1 building running Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.
No power for computing yetThe cooling towers for Buildings 2 and 3 are both a little less than half done and the buildings still look like active construction sites.
No power for computing yetBuilding 2 looks externally complete
No power for computing yetAfter a long quiet period they've laid foundations for Building 2 and the substation.
No power for computing yetRoof complete on Building 1 (the 'H'), although we suspect this building is not for AI compute due to the construction speed, irregular design, and lack of external cooling.
No power for computing yetFirst signs of development/land clearing
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Aug 19, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google DeepMind (possibly)
No wider project named
Not named
Not named
Fort Wayne, Indiana
Address in Epoch AI's records: 6015 Adams Center Road, Fort Wayne, IN 46806.
Also in Indiana
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Google's plans for wetlands in Fort Waynethelocalfw.com
- Data center's diesel generatorsthelocalfw.com
- Project's history and tax abatementthelocalfw.com
- City Council approvalcitycouncildocuments.acfw.net
- Google Fort Wayne in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-fort-wayne