Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
According to schedule, Building 3 should come online in the first half of 2027. That would bring the full PF1 campus to 400 MW, according to the contract.
400 MW for computing (was 88 MW)520 MW in all3 buildings running - Epoch AI's projection
According to the schedule, Building 2 should be online sometime in the second half of 2026. We can estimate the end of 2026 for 250 MW operational.
88 MW for computing (was 68 MW)114 MW in all2 buildings running According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.
68 MW for computing88 MW in all1 building runningAccording to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, though it's very safe to assume they're under construction at this stage, considering they're still under construction in the satellite image 3 months from now.)
68 MW for computing88 MW in all1 building runningThis Applied Digital report says the rest of Building 1 has reached Ready for Service, bringing the first building to its expected 100 MW. We can treat this as the first completed data center building.
68 MW for computing (was 50 MW)88 MW in all1 building runningThe first 50 MW slice of Building 1 has reached Ready for Service status according to this report. This is the first point where we would count any CoreWeave capacity as operational.
50 MW for computing65 MW in all1 building runningA new 150 MW lease brings CoreWeave to 400 MW total contracted. The project is now clearly scheduled to be a three-building CoreWeave campus.
No power for computing yetCoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an SEC 8-k filing from this date.
No power for computing yetStart of construction for the first building, according to Applied Digital. CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jun 30, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B200 | Nvidia | 36,900 est. | Nov 24, 2025 | Building 1 reached full service on this date, but the chip count uses the sheet's cooling-based modeled Building 1 IT load of 67.7 MW instead of the officially disclosed 100 MW critical IT load. |
Ellendale, North Dakota
Address in Epoch AI's records: 9685 87th Ave SE, Ellendale, ND 58436.
More of CoreWeave's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Applied Digital Announces 250MW AI Data Center Lease With CoreWeaveir.applieddigital.com
- SEC 8k Filing with Applied Digitalir.applieddigital.com
- Applied Digital Delivers Second Building at Polaris Forge 1ir.applieddigital.com
- CoreWeave Ellendale ND in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-ellendale-nd