Running and growing · Ellendale, North Dakota

CoreWeave Ellendale ND

CoreWeave Ellendale ND is an AI data center in Ellendale, North Dakota, owned by CoreWeave and used by OpenAI (possibly). Epoch AI estimates it draws 68 MW for computing, rising to 400 MW by Jun 2027.

  • 68 MWfor computing now, #64 of the 96 Epoch AI tracks
  • 400 MWplanned by Jun 2027
  • $2.6 billionbuilt so far, Epoch AI's estimate in 2025 dollars
68 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW100 MW200 MW300 MW400 MW500 MW2024202520262027Oct 31, 2023: 0 MWOct 27, 2025: 50 MWNov 24, 2025: 68 MWDec 31, 2026: 88 MW (projected)Jun 1, 2027: 400 MW (projected)0 MW100 MW200 MW300 MW400 MW500 MW2024202520262027Oct 31, 2023: 0 MWOct 27, 2025: 50 MWNov 24, 2025: 68 MWDec 31, 2026: 88 MW (projected)Jun 1, 2027: 400 MW (projected)
  1. Epoch AI's projection

    According to schedule, Building 3 should come online in the first half of 2027. That would bring the full PF1 campus to 400 MW, according to the contract.

    400 MW for computing (was 88 MW)520 MW in all3 buildings running
  2. Epoch AI's projection

    According to the schedule, Building 2 should be online sometime in the second half of 2026. We can estimate the end of 2026 for 250 MW operational.

    88 MW for computing (was 68 MW)114 MW in all2 buildings running
  3. According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.

    68 MW for computing88 MW in all1 building running
  4. According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, though it's very safe to assume they're under construction at this stage, considering they're still under construction in the satellite image 3 months from now.)

    68 MW for computing88 MW in all1 building running
  5. This Applied Digital report says the rest of Building 1 has reached Ready for Service, bringing the first building to its expected 100 MW. We can treat this as the first completed data center building.

    68 MW for computing (was 50 MW)88 MW in all1 building running
  6. The first 50 MW slice of Building 1 has reached Ready for Service status according to this report. This is the first point where we would count any CoreWeave capacity as operational.

    50 MW for computing65 MW in all1 building running
  7. A new 150 MW lease brings CoreWeave to 400 MW total contracted. The project is now clearly scheduled to be a three-building CoreWeave campus.

    No power for computing yet
  8. CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an SEC 8-k filing from this date.

    No power for computing yet
  9. Start of construction for the first building, according to Applied Digital. CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Jun 30, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

68 MWIT power, for the computersJun 30, 2026
88 MWtotal power, cooling included
400 MWIT power planned by Jun 2027
93,000computing power, counted as Nvidia H100 chips
$2.6 billioncapital cost so far: $1.8 billion for chips and computers, $0.8 billion for the buildings, power and land
$15 billioncapital cost once finished, by Jun 2027
$0.1 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

CoreWeave

Uses it

OpenAI (possibly)

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
B200Nvidia36,900 est.Nov 24, 2025Building 1 reached full service on this date, but the chip count uses the sheet's cooling-based modeled Building 1 IT load of 67.7 MW instead of the officially disclosed 100 MW critical IT load.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Applied Digital Announces 250MW AI Data Center Lease With CoreWeaveir.applieddigital.com
  2. SEC 8k Filing with Applied Digitalir.applieddigital.com
  3. Applied Digital Delivers Second Building at Polaris Forge 1ir.applieddigital.com
  4. CoreWeave Ellendale ND in Epoch AI's directoryepoch.ai
  5. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-ellendale-nd