Being built · Cedar Rapids, Iowa

Google Cedar Rapids

Google Cedar Rapids is an AI data center in Cedar Rapids, Iowa, owned by Google and used by Google DeepMind (possibly). It is being built; Epoch AI projects 261 MW for computing by May 2027.

  • 261 MWplanned by May 2027
Being built
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW100 MW200 MW300 MW202520262027Jun 14, 2024: 0 MWDec 31, 2026: 87 MW (projected)Feb 22, 2027: 174 MW (projected)May 23, 2027: 261 MW (projected)0 MW100 MW200 MW300 MW202520262027Jun 14, 2024: 0 MWDec 31, 2026: 87 MW (projected)Feb 22, 2027: 174 MW (projected)May 23, 2027: 261 MW (projected)
  1. Epoch AI's projection

    Building 3 is operational. Earlier satellite images suggest it was about 3 months behind Building 2.

    261 MW for computing (was 174 MW)314 MW in all3 buildings running
  2. Epoch AI's projection

    Building 2 is operational. Based on Google Omaha Building 3 taking about 14 months from starting the roof to operation.

    174 MW for computing (was 87 MW)209 MW in all2 buildings running
  3. Epoch AI's projection

    Building 1 is operational. There is still work to be done since April, and Q4 2026 operational estimate was based on visible progress then.

    87 MW for computing105 MW in all1 building running
  4. Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators.

    No power for computing yet
  5. About half of Building 1 generators are in place. Building 2 roofing has started - about where Google Omaha Building 3 was on 2025-03-16.

    No power for computing yet
  6. Building 1 cooling towers and generators starting to be put in place. There's a foundation for Building 2 and 3.

    No power for computing yet
  7. Land clearing begins.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Apr 16, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

None yetIT power, for the computersApr 16, 2026
None yettotal power, cooling included
261 MWIT power planned by May 2027
None yetcomputing power, counted as Nvidia H100 chips
–capital cost so far
$9.9 billioncapital cost once finished, by May 2027
–a year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Google

Uses it

Google DeepMind (possibly)

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. MISO new load announcementscdn.misoenergy.org
  2. Permit applicationgovonlinesaas.com
  3. Google Cedar Rapids in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-cedar-rapids