Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 2 is estimated to be operational, based on all external equipment being installed, and ordinary cars parked by the building.
154 MW for computing (was 77 MW)185 MW in all2 buildings runningBuilding 1 is estimated to be operational, based on all external equipment being installed.
77 MW for computing93 MW in all1 building runningLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Apr 29, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v7 | 34,648 est. | Apr 29, 2026 | Building 2 (operational 2026-04-29): v7 share of the Q1 FY26 mix (lagged one quarter from the operational date to account for purchase-to-operation delay), applied to Building 2's incremental IT power. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v6e | 78,028 est. | Apr 29, 2026 | Building 1+2 cumulative v6e: Building 1 (Q1 FY25 lagged mix) plus Building 2's v6e share (Q1 FY26 mix; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5p | 24,736 est. | Apr 29, 2026 | Building 1+2 cumulative v5p: all from Building 1 (Q1 FY25 lagged mix). Building 2's lagged quarter (Q1 FY26) adds no v5p, so unchanged from Building 1. | |
| TPU v5e | 54,734 est. | Apr 29, 2026 | Building 1+2 cumulative v5e: all from Building 1 (Q1 FY25 lagged mix). Building 2's lagged quarter (Q1 FY26) adds no v5e, so unchanged from Building 1. |
The Dalles, Oregon
Address in Epoch AI's records: 3500 River Rd, The Dalles, OR.
Also in Oregon
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Permit confirming this is a data center and the internal square footagestatic1.squarespace.com
- Google PUE data listing the "3rd facility" from Q3 2025datacenters.google
- Google The Dalles in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-the-dalles