Wednesday, November 25, 2026 · Edition updated 6:00 AM ETWED, NOV 25 editionNext edition in Next in --:--:--
Intelligence Progress
Running and growing · Mount Pleasant, Wisconsin

Microsoft Fairwater Wisconsin

Microsoft Fairwater Wisconsin is an AI data center in Mount Pleasant, Wisconsin, owned by Microsoft and used by OpenAI (likely), Microsoft (likely). Epoch AI estimates it draws 369 MW for computing, rising to 2.26 GW by May 2028.

  • 369 MWfor computing now, #8 of the 96 Epoch AI tracks
  • 2.26 GWplanned by May 2028
  • $14 billionbuilt so far, Epoch AI's estimate in 2025 dollars
369 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW500 MW1 GW1.5 GW2 GW2.5 GW20242025202620272028Jul 14, 2023: 0 MWApr 16, 2026: 369 MWFeb 20, 2027: 737 MW (projected)May 13, 2028: 2.26 GW (projected)0 MW500 MW1 GW1.5 GW2 GW2.5 GW20242025202620272028Jul 14, 2023: 0 MWApr 16, 2026: 369 MWFeb 20, 2027: 737 MW (projected)May 13, 2028: 2.26 GW (projected)
  1. Epoch AI's projection

    Buildings 3-11 are estimated to be operational. The grading for this revised 9-building plan was underway in May 2026, and we assume an average 2-year build time from that point.

    2.26 GW for computing (was 737 MW)2.71 GW in all11 buildings running
  2. Epoch AI's projection

    Building 2 is operational. This is estimated based on (1) the delay between Building 1 and Building 2 starting land clearing, (2) in March 2025, a Microsoft spokesperson said “fully on track” with the first phase , where “southern datacenter buildings complete, and preparation begins for operations” was expected by late 2026. Finally, while it's not 100% consistent with our estimates, MISO was planning 1480 MW of load for Microsoft in Mount Pleasant in 2026.

    737 MW for computing (was 369 MW)885 MW in all2 buildings running
  3. The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2.

    369 MW for computing442 MW in all1 building running
  4. Building 1 is operational. X post from Microsoft saying this date for Fairwater becoming operational.

    369 MW for computing442 MW in all1 building running
  5. Building 1 looks complete, but based on Microsoft announcements, it's not fully operational yet. Steel framing is underway for Building 2.

    No power for computing yet
  6. Building 1 cooling and backup generators all look complete from above but there is still construction visible around the building. Building 2 is well underway with a foundation and a complete substation. Large carpark and concrete area north of Building 2. Building 3 has a concrete foundation and a substation underway.

    No power for computing yet
  7. Land clearing begins for Building 1.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of May 15, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

369 MWIT power, for the computersMay 15, 2026
442 MWtotal power, cooling included
2.26 GWIT power planned by May 2028
446,000computing power, counted as Nvidia H100 chips
$14 billioncapital cost so far: $9.6 billion for chips and computers, $4.3 billion for the buildings, power and land
$86 billioncapital cost once finished, by May 2028
$0.3 billiona year to run (power, staff, upkeep, taxes, water)
7,710 gallonsof water a day, Epoch AI's estimate (Apr 16, 2026)

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Microsoft

Uses it

OpenAI (likely), Microsoft (likely)

Part of

Microsoft AI WAN

Investors

Not named

Builders

Not named

Power from

WE Energies

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
B200Nvidia176,391 est.Apr 16, 2026GB200 NVL72 confirmed by Microsoft (blog post). Building 1. Count based on estimated IT power and FP8 performance model, using the standardized GB200 NVL72 server assumed values and B200 per-chip performance. This is consistent with Microsoft's statement that Fairwater uses "hundreds of thousands of NVIDIA GB200s" (Satya Nadella).
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Microsoft blog with engineering detailsblogs.microsoft.com
  2. Microsoft blog with more general informationblogs.microsoft.com
  3. Construction Permit Application for building 1drive.google.com
  4. Plan for 9-building and 6-building expansionsdrive.google.com
  5. OpenAI article mentioning they use Microsoft's Fairwater supercomputersopenai.com
  6. Microsoft Fairwater Wisconsin in Epoch AI's directoryepoch.ai
  7. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/microsoft-fairwater-wisconsin