Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Buildings 3-11 are estimated to be operational. The grading for this revised 9-building plan was underway in May 2026, and we assume an average 2-year build time from that point.
2.26 GW for computing (was 737 MW)2.71 GW in all11 buildings running - Epoch AI's projection
Building 2 is operational. This is estimated based on (1) the delay between Building 1 and Building 2 starting land clearing, (2) in March 2025, a Microsoft spokesperson said “fully on track” with the first phase , where “southern datacenter buildings complete, and preparation begins for operations” was expected by late 2026. Finally, while it's not 100% consistent with our estimates, MISO was planning 1480 MW of load for Microsoft in Mount Pleasant in 2026.
737 MW for computing (was 369 MW)885 MW in all2 buildings running The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2.
369 MW for computing442 MW in all1 building runningBuilding 1 is operational. X post from Microsoft saying this date for Fairwater becoming operational.
369 MW for computing442 MW in all1 building runningBuilding 1 looks complete, but based on Microsoft announcements, it's not fully operational yet. Steel framing is underway for Building 2.
No power for computing yetBuilding 1 cooling and backup generators all look complete from above but there is still construction visible around the building. Building 2 is well underway with a foundation and a complete substation. Large carpark and concrete area north of Building 2. Building 3 has a concrete foundation and a substation underway.
No power for computing yetLand clearing begins for Building 1.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 15, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B200 | Nvidia | 176,391 est. | Apr 16, 2026 | GB200 NVL72 confirmed by Microsoft (blog post). Building 1. Count based on estimated IT power and FP8 performance model, using the standardized GB200 NVL72 server assumed values and B200 per-chip performance. This is consistent with Microsoft's statement that Fairwater uses "hundreds of thousands of NVIDIA GB200s" (Satya Nadella). |
Mount Pleasant, Wisconsin
Address in Epoch AI's records: 4800 90th St, Mount Pleasant, WI 53403.
Also in Wisconsin
More of Microsoft's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Microsoft blog with engineering detailsblogs.microsoft.com
- Microsoft blog with more general informationblogs.microsoft.com
- Construction Permit Application for building 1drive.google.com
- Plan for 9-building and 6-building expansionsdrive.google.com
- OpenAI article mentioning they use Microsoft's Fairwater supercomputersopenai.com
- Microsoft Fairwater Wisconsin in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/microsoft-fairwater-wisconsin