Intelligence Progress
AI data centers by company

ByteDance's AI data centers.

ByteDance owns the chips at 2 of the 96 AI data centers Epoch AI tracks, drawing 464 MW for computing now and 943 MW once its projects finish. It uses 2 sites, some of them by Epoch AI's best guess.

  • 2sites where it owns the chips
  • 464 MWfor computing now
  • 943 MWplanned, if every project finishes
Its power over time

464 MW now, 943 MW planned.

Power for computing at the sites where ByteDance owns the chips, month by month. After today it is Epoch AI's projection. Built so far: about $18 billion, by Epoch's cost model.

  • ByteDance
  • Projected by Epoch AI
00.25 GW0.5 GW0.75 GW1 GW20232024202520262027202820292030TodayProjected
The numbers, year by year
End ofByteDanceAll
202219 MW19 MW
202361 MW61 MW
2024114 MW114 MW
2025464 MW464 MW
2026*464 MW464 MW
2027*943 MW943 MW
2028*943 MW943 MW
2029*943 MW943 MW
Jan 2030*943 MW943 MW

IT power. * Epoch AI's projection.

Used · 2

Where it trains and runs.

Sites where Epoch AI records it as a user, whoever owns the chips. Who uses a site is often kept quiet, so each says how sure Epoch is.

  1. RunningBridge Data Centres MY06Sedenak Tech Park, Johor, Malaysia · ByteDance (likely)243 MW nowEpoch AI says likely
  2. Running and growingVNET Bayin UlanqabUlanqab, China · ByteDance (possibly)221 MW now700 MW by Sep 2027Epoch AI says possibly
Where

In 2 places.

From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Owner means the company that owns the chips; Epoch notes it may differ from who owns or runs the building. Next change Epoch projects: VNET Bayin Ulanqab, 700 MW by Sep 1, 2027.