Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Buildings 3-4 operational. Based on Bravida stating that installation work in another EcoDataCenter data center continues through Q1 2028, combined with permit documentation showing four data center buildings under construction by May 2026.
48 MW for computing (was 24 MW)67 MW in all4 buildings running - Epoch AI's projection
Buildings 1-2 operational. Based on Bravida stating that installation work in two EcoDataCenter data centers in Borlänge is expected to be completed by mid-2027, together with EcoDataCenter Annual Report 2025 identifying B1 and B2 as the first two buildings under construction.
24 MW for computing34 MW in all2 buildings running Buildings 1 and 2 look fully roofed, with active construction showing cooling and power equipment still being installed. Buildings 3-4 look like their foundations have been laid out and are early in construction.
No power for computing yetBuildings 1 and 2 still under construction. The first two building shells are visibly well into construction, with lots of additional ground work visible all across the campus. Based on high-resolution satellite imagery from this date.
No power for computing yetLand clearing begins. EcoDataCenter announces on September 24th that construction has started on EcoDataCenter 2, so we model it as started from the beginning of the month.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Aug 17, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
No wider project named
Not named
Not named
Not named
Borlänge, Sweden
Address in Epoch AI's records: Kvarnsvedsvägen 420, 784 66 Borlänge, Sweden.
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- EcoDataCenter 2 campus overviewecodatacenter.tech
- EcoDataCenter 2025 Annual Reportecodatacenter.tech
- EcoDataCenter groundbreaking announcementecodatacenter.tech
- Mistral AI partnership announcementecodatacenter.tech
- EcoDataCenter 2 in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/ecodatacenter-2