Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 4 and 5 are operational, based on Building 5 being roughly 1 year behind Building 1 in satellite imagery.
240 MW for computing (was 144 MW)336 MW in all5 buildings running Building 2 and 3 are operational, based on the previous entry.
144 MW for computing (was 48 MW)202 MW in all3 buildings runningBuilding 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the perimeter and no cars in the carpark, but we expect they will be operational within 3 months. Building 4 has complete chillers and backup generators, while Building 5 has chillers but only a few backup generators - roughly the state of Building 1 on 2025-02-04.
48 MW for computing67 MW in all1 building runningThe substation looks complete, but we expect Building 1 still needs commissioning before it is fully operational.
No power for computing yetThe substation is still under construction, based on a Google Earth image, so we don't think any buildings are operational yet.
No power for computing yetBuilding 1 shell is mostly complete, with some chillers installed on the roof. Building 2 shell is under construction.
No power for computing yetLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 14, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not named by Epoch AI
Not known
No wider project named
Not named
Not named
Dominion Energy
Sandston, Virginia
Address in Epoch AI's records: 3525–3543 Portugee Rd, Sandston, VA 23150.
Also in Virginia
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Richmond 3 factsheetq.com
- Environmental permit detailing power generationdeq.virginia.gov
- QTS Richmond 3 in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/qts-richmond-3