QTS Richmond 3

QTS Richmond 3 is an AI data center in Sandston, Virginia. Epoch AI estimates it draws 144 MW for computing, rising to 240 MW by Feb 2027.

  • 144 MWfor computing now, #42 of the 96 Epoch AI tracks
  • 240 MWplanned by Feb 2027
  • $5.5 billionbuilt so far, Epoch AI's estimate in 2025 dollars
144 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW200 MW250 MW300 MW202520262027Apr 1, 2024: 0 MWFeb 13, 2026: 48 MWMay 14, 2026: 144 MWFeb 13, 2027: 240 MW (projected)0 MW50 MW100 MW150 MW200 MW250 MW300 MW202520262027Apr 1, 2024: 0 MWFeb 13, 2026: 48 MWMay 14, 2026: 144 MWFeb 13, 2027: 240 MW (projected)
  1. Epoch AI's projection

    Building 4 and 5 are operational, based on Building 5 being roughly 1 year behind Building 1 in satellite imagery.

    240 MW for computing (was 144 MW)336 MW in all5 buildings running
  2. Building 2 and 3 are operational, based on the previous entry.

    144 MW for computing (was 48 MW)202 MW in all3 buildings running
  3. Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the perimeter and no cars in the carpark, but we expect they will be operational within 3 months. Building 4 has complete chillers and backup generators, while Building 5 has chillers but only a few backup generators - roughly the state of Building 1 on 2025-02-04.

    48 MW for computing67 MW in all1 building running
  4. The substation looks complete, but we expect Building 1 still needs commissioning before it is fully operational.

    No power for computing yet
  5. The substation is still under construction, based on a Google Earth image, so we don't think any buildings are operational yet.

    No power for computing yet
  6. Building 1 shell is mostly complete, with some chillers installed on the roof. Building 2 shell is under construction.

    No power for computing yet
  7. Land clearing begins.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of May 14, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

144 MWIT power, for the computersMay 14, 2026
202 MWtotal power, cooling included
240 MWIT power planned by Feb 2027
175,000computing power, counted as Nvidia H100 chips
$5.5 billioncapital cost so far: $3.8 billion for chips and computers, $1.7 billion for the buildings, power and land
$9.1 billioncapital cost once finished, by Feb 2027
$0.1 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Not named by Epoch AI

Uses it

Not known

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Dominion Energy

Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Richmond 3 factsheetq.com
  2. Environmental permit detailing power generationdeq.virginia.gov
  3. QTS Richmond 3 in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/qts-richmond-3