Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Estimate: All 6 AI data center buildings will be finished in 2028, assuming a groundbreak-to-operational timeline of 18-24 months. One is complete, three are clearly under construction, and the last two data centers are still breaking ground and laying foundations.
348 MW for computing (was 85 MW)487 MW in all6 buildings running All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery.
85 MW for computing118 MW in all1 building runningBuilding 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satellite imagery (a clear image of this can be seen on July 29 via Google Earth).
85 MW for computing118 MW in all1 building runningLand clearing begins by Peterson Companies for Stack Infrastructure, which is noted in the news and visible on satellite imagery.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Feb 14, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not named by Epoch AI
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| H100 | Nvidia | 60,911 est. | Oct 1, 2024 | H100 assumed from 62% market share in Q2 2024 and 8 chips per server (HGX form factor). Count = IT capacity (from air-cooled chiller fan count model) / server power × 8 chips per server. |
Manassas, Virginia
Address in Epoch AI's records: 9590 Hornbaker Rd, Manassas, VA 20109.
Also in Virginia
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Official website for NVA02, showcasing their project.stackinfra.com
- Most recent official schematic of the NVA02 campus.stackinfra.com
- Air quality permit from the state of Virginia.deq.virginia.gov
- STACK Infrastructure NVA02 in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/stack-infrastructure-nva02