Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Foundations appear to be underway for Building 5 and 6, just north of Building 4.
202 MW for computing263 MW in all4 buildings runningConfirmation that Building 3 and 4 look complete.
202 MW for computing263 MW in all4 buildings runningBuilding 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
202 MW for computing (was 81 MW)263 MW in all4 buildings runningBuilding 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
81 MW for computing (was 40 MW)105 MW in all2 buildings runningBuilding 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
40 MW for computing53 MW in all1 building runningLand clearing begins for Building 1.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Apr 27, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B200 | Nvidia | 58,121 est. | Sep 1, 2025 | GB200 NVL72 assumed from operational date (Q3 2025) and insufficient cooling for B200 power density. Count = 2 buildings × chips per building, from chiller-based IT capacity / server power × 72. |
| H100 | Nvidia | 58,302 est. | Jan 16, 2025 | Building 2 also H100. Count = cumulative H100s across Buildings 1 and 2, each derived from IT capacity / server power × 8. |
Goodyear, Arizona
Address in Epoch AI's records: 14250 W Broadway Rd, Goodyear, AZ 85338.
Also in Arizona
More of Microsoft's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Maricopa County mapgis.maricopa.gov
- Dust control permitedms.maricopa.gov
- SemiAnalysis articlenewsletter.semianalysis.com
- Microsoft Goodyear in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/microsoft-goodyear