Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 8 projected operational. TDLR project TABS2026028247 schedules Building A's data-hall fit-out for completion by this date.
282 MW for computing (was 262 MW)395 MW in all8 buildings running Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.
262 MW for computing367 MW in all7 buildings runningBuildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026.
262 MW for computing (was 131 MW)367 MW in all7 buildings runningBuildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an earnings call from this date.
131 MW for computing183 MW in all4 buildings runningBuildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery.
131 MW for computing (was 67 MW)183 MW in all4 buildings runningHalf the campus energized. 67 billable MW are now dedicated to CoreWeave's GPUs across three buildings.
67 MW for computing (was 8 MW)94 MW in all3 buildings runningFirst 8 MW billable tranche dedicated to AI starts running at the site, with another 40 scheduled by the end of the quarter.
8 MW for computing11 MW in all1 building runningConstruction start - The Texas Department of Licensing and Regulation reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Sep 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B200 | Nvidia | 100,000 est. | Jul 3, 2026 | This is the estimated final CoreWeave AI load. Since it's disclosed to be >50,000 GPUs at ~130 MW, a safe estimate can be 100,000 GPUs at the full 260 MW. (MarketBeat) |
Denton, Texas
Address in Epoch AI's records: 8171 Jim Christal Rd, Denton, TX 76207.
Also in Texas
More of CoreWeave's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Core Scientific - CoreWeave Announce 1.2B expansion in Denton, TXinvestors.corescientific.com
- Core Scientific - Denton Datacenter Official Sitecorescientific.com
- TMF - Core Scientific Q4 2025 Earnings Transcriptfool.com
- WSJ - plans to rent to OpenAIwsj.com
- CoreWeave Denton TX in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-denton-tx