Being built · Al Dhafrah, Abu Dhabi, United Arab Emirates

OpenAI Stargate UAE

OpenAI Stargate UAE is an AI data center in Al Dhafrah, Abu Dhabi, United Arab Emirates, owned by G42 (likely) and used by OpenAI. It is being built; Epoch AI projects 1.00 GW for computing by Jan 2028.

  • 1.00 GWplanned by Jan 2028
Being built
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW200 MW400 MW600 MW800 MW1 GW1.2 GW202620272028Jun 9, 2025: 0 MWDec 1, 2026: 200 MW (projected)Jan 1, 2028: 1.00 GW (projected)0 MW200 MW400 MW600 MW800 MW1 GW1.2 GW202620272028Jun 9, 2025: 0 MWDec 1, 2026: 200 MW (projected)Jan 1, 2028: 1.00 GW (projected)
  1. Epoch AI's projection

    1 GW of IT power is operational. We haven’t seen expansion beyond 200 MW as of November 2025. Optimistically, 8 more 100 MW buildings start construction in December 2025, in parallel, and take 1.5 years like the first two buildings, hitting 1 GW by Q3 2027. More realistically, there's some staggering of construction over several months, like Stargate Abilene. Our median estimate is January 2028.

    1.00 GW for computing (was 200 MW)1.40 GW in all10 buildings running
  2. Epoch AI's projection

    Building 1 and 2 are operational. The similar data center in Ajman, UAE was delayed by over a year, now due in December 2026 (compare 1, 2). The buildings here looked 3-6 months behind the Ajman building as of November 2025, but they were moving faster. So we think Building 1 and 2 are on track for 200 MW by December 2026, along with the Ajman building.

    200 MW for computing280 MW in all2 buildings running
  3. Building 1 and 2 are partly constructed. No clear evidence of more buildings starting construction.

    No power for computing yet
  4. Land clearing begins for Building 1 and 2

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Nov 16, 2025. IT power is what the computers draw; the total adds cooling and the rest of the building.

None yetIT power, for the computersNov 16, 2025
None yettotal power, cooling included
1.00 GWIT power planned by Jan 2028
None yetcomputing power, counted as Nvidia H100 chips
–capital cost so far
$38 billioncapital cost once finished, by Jan 2028
–a year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

G42 (likely)

Uses it

OpenAI

Part of

Stargate

Investors

Softbank, Oracle, NVIDIA, Cisco, G42

Builders

Not named

Power from

Not named

Where it is

Al Dhafrah, Abu Dhabi, United Arab Emirates

Address in Epoch AI's records: Nexus L&T Project Office, Al Bihouth, Al Dhafrah, Abu Dhabi, United Arab Emirates.

Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. News update with timelapse of constructionkhaleejtimes.com
  2. Announcement of the (separate) 100 MW Khazna Ajman data centerkhaznadatacenters.com
  3. News about the US approval of NVIDIA chips in the UAEbloomberg.com
  4. OpenAI Stargate UAE in Epoch AI's directoryepoch.ai
  5. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/openai-stargate-uae