Wednesday, November 25, 2026 · Edition updated 6:00 AM ETWED, NOV 25 editionNext edition in Next in --:--:--
Intelligence Progress
Being built · Burlington, Texas

OpenAI Stargate Milam

OpenAI Stargate Milam is an AI data center in Burlington, Texas, owned by Softbank and used by OpenAI. It is being built; Epoch AI projects 857 MW for computing by Dec 2028.

  • 857 MWplanned by Dec 2028
Being built
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW200 MW400 MW600 MW800 MW1 GW202620272028Sep 27, 2025: 0 MWDec 31, 2028: 857 MW (projected)0 MW200 MW400 MW600 MW800 MW1 GW202620272028Sep 27, 2025: 0 MWDec 31, 2028: 857 MW (projected)
  1. Epoch AI's projection

    All buildings finished, site is fully operational. Our reasoning is that examples so far take a median of 2-2.5 years to go from land clearing to 1 GW. This suggests around 2028-01-01 here. However, due to delays being more likely than speedups and the fact that this base rate data is still unproven, the more conservative estimate is made. The current state of the site also supports this estimation.

    857 MW for computing1.20 GW in all
  2. Steel framing and roofing is underway for Building 1.

    No power for computing yet
  3. Small sections of building foundation construction begins, and land clearing appears to be mostly finished

    No power for computing yet
  4. Land clearing begins for the site

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Mar 23, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

None yetIT power, for the computersMar 23, 2026
None yettotal power, cooling included
857 MWIT power planned by Dec 2028
None yetcomputing power, counted as Nvidia H100 chips
–capital cost so far
$32 billioncapital cost once finished, by Dec 2028
–a year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Softbank

Uses it

OpenAI

Part of

Stargate

Investors

Not named

Builders

Not named

Power from

Not named

Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Data Center Dynamics article on the sitedatacenterdynamics.com
  2. SB Energy article, source for 1.2 GW capacitysbenergy.com
  3. TDLR page for the first building of the site, indicating construction completion datetdlr.texas.gov
  4. OpenAI Stargate Milam in Epoch AI's directoryepoch.ai
  5. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/openai-stargate-milam