1.52 GW now, 4.08 GW planned.
Power for computing at the sites where Microsoft owns the chips, month by month. After today it is Epoch AI's projection. Built so far: about $58 billion, by Epoch's cost model.
- Microsoft
- Projected by Epoch AI
The numbers, year by year
| End of | Microsoft | All |
|---|---|---|
| 2021 | 48 MW | 48 MW |
| 2022 | 48 MW | 48 MW |
| 2023 | 135 MW | 135 MW |
| 2024 | 201 MW | 201 MW |
| 2025 | 807 MW | 807 MW |
| 2026* | 1.5 GW | 1.5 GW |
| 2027* | 2.6 GW | 2.6 GW |
| 2028* | 4.1 GW | 4.1 GW |
| 2029* | 4.1 GW | 4.1 GW |
| Jan 2030* | 4.1 GW | 4.1 GW |
IT power. * Epoch AI's projection.
Where it owns the chips.
Largest first, by power drawn now. Each opens the site's full record.
- RunningMicrosoft Fairwater AtlantaFayetteville, Georgia · Microsoft636 MW now
- Running and growingMicrosoft Fairwater WisconsinMount Pleasant, Wisconsin · Microsoft369 MW now2.26 GW by May 2028
- RunningMicrosoft GoodyearGoodyear, Arizona · Microsoft202 MW now
- RunningMicrosoft Project OsmiumCumming, Iowa · Microsoft190 MW now
- RunningMicrosoft SAT40San Antonio, Texas · Microsoft75 MW now
- RunningMicrosoft SAT14San Antonio, Texas · Microsoft47 MW now
- Being builtCrusoe Abilene ExpansionAbilene, Texas · MicrosoftNot drawing power yet672 MW by Nov 2027
Where it trains and runs.
Sites where Epoch AI records it as a user, whoever owns the chips. Who uses a site is often kept quiet, so each says how sure Epoch is.
- RunningMicrosoft Fairwater AtlantaFayetteville, Georgia · Microsoft636 MW nowEpoch AI says likely
- Running and growingMicrosoft Fairwater WisconsinMount Pleasant, Wisconsin · Microsoft369 MW now2.26 GW by May 2028Epoch AI says likely
- RunningMicrosoft GoodyearGoodyear, Arizona · Microsoft202 MW now
- Running and growingNebius MantsalaMäntsälä, Uusimaa, Finland · Nebius75 MW now145 MW by Dec 2027Epoch AI says possibly
- RunningMicrosoft-Nebius New JerseyVineland, New Jersey · Nebius50 MW nowEpoch AI says likely
- Running and growingStart Campus Sines Data CampusSines, Portugal · Nscale33 MW now233 MW by Sep 2027
- Being builtCrusoe Abilene ExpansionAbilene, Texas · MicrosoftNot drawing power yet672 MW by Nov 2027Epoch AI says likely
- Being builtMicrosoft Narvik NorwayBjerkvik, Narvik, Norway · Nscale (likely)Not drawing power yet92 MW by Dec 2026Epoch AI says likely
In 9 places.
From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Owner means the company that owns the chips; Epoch notes it may differ from who owns or runs the building. Next change Epoch projects: Microsoft Fairwater Wisconsin, 737 MW by Feb 20, 2027.